Scheduled Concrete Repair - I-24 Westbound through Downtown Chattanooga - Weekend of January 29-February 1, 2021

CHATTANOOGA, Tenn. – TDOT contract crews will make concrete repairs this weekend on I-24 West in Hamilton County between mile markers 177 and 179 in lane #2 (right lane). The repair work will begin at 8:00 p.m. EST on Friday, January 29, 2021 and end by or before 6:00 a.m. EST on Monday, February 1, 2021. During the work, lane #2 on I-24 West and the Williams Street on-ramp to I-24 West will be closed. Lane #1 (left lane) on I-24 West will remain open to traffic.
This work will consist of sawing and removing
damaged concrete slabs and re-pouring them with new concrete, which will need
several hours to harden enough to handle traffic. As soon as the concrete hardens
enough to pass strength tests, all lanes will be reopened to traffic.
In preparation for removing and replacing the
damaged concrete, the contractor will saw cut the damaged areas of concrete on
Thursday night, January 28, 2021 beginning at 9:00 p.m. EST and ending by
Friday morning, January 29, 2021 at 6:00 a.m. EST. During this work, lane #2 on
I-24 West and the Williams Street on-ramp to I-24 West will be closed to
traffic. I-24 West and the Williams Street on-ramp will be reopened to traffic
on Friday morning and stay open until the repair work begins on Friday night at
8:00 p.m. at which time both of them will be closed once again.
During the work, the Tennessee Highway Patrol
and a truck-mounted attenuator with a message board will be on site to assist
with traffic control and information. A message board will be in place on
Williams Street, and detour signs will be installed to direct traffic entering
I-24 West from the downtown area. Drivers are urged to obey the signage and pay
close attention to changing conditions in the work zone.
This concrete repair work is being done as part
of a statewide on-call concrete repair contract. This work is weather
dependent. Should weather or unforeseen circumstances postpone this work, it
will be rescheduled to take place as soon as possible.
From your desktop or
mobile device, get the latest construction activity and live-streaming SmartWay
traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any landline
or cell phone for travel information or follow us on Twitter at any of TDOT’s
Twitter pages.
As
always, drivers are reminded to use all motorist information tools wisely and “Know
Before You Go!” by checking travel conditions before leaving for your
destination. Drivers should never tweet, text or talk on a cell phone while
behind the wheel.
# # #
Roadway Activity Report -TDOT Region 2 - Jan. 28-Feb 3, 2021
ROADWAY ACTIVITY REPORT – REGION 2
(Parts of East and Middle Tennessee)
January 28 – February 3, 2021
DISTRICT 27
CLAY
COUNTY SR-53 bridge repair over Dry Fork Creek (LM 1.3) and Mill Creek (LM
2.5): The
contractor will be on site continuing bridge repair work at Mill Creek and Dry
Fork Bridges located at LM 1.35 and 2.50. The southbound lane of SR-53 will
remain closed during Phase 1 on both bridges; the northbound lane will be
closed during Phase 2 on both bridges. Lane closures will be in effect until
the contract completion on 06/30/21. Motorists are encouraged to use caution
through the work zone and obey posted speed limit. RESTRICTIONS: Loads wider than 11'
should seek alternate route.
[Mid-State
Construction Company, Inc./Moore/CNU198]
CUMBERLAND
COUNTY SR-101 (Peavine Road) grading, drainage, and paving from Firetower Road
to Westchester/Catoosa Boulevard: Motorists should use caution while driving along
Peavine Road and be alert for changes in traffic patterns. The posted speed
limit has been reduced from 45 MPH to 35 MPH within the work zone. Temporary
lane closures and/or traffic stoppages may be needed as construction activities
continue. Motorists should reduce speed on Peavine Road and be alert for
construction personnel/equipment entering and exiting the roadway.
[Rogers
Group, Inc./Bradley/CNQ921]
DEKALB
AND WARREN COUNTY SR-56 construction of bridges and paving from south of
Warren-Dekalb county line (LM 24.5) to East Bryant St. (LM 2.9): The contractor will continue
installing concrete box culverts and drainage structures. Grade work, bridge
work, paving operations, and utility work on the new roadway alignment are
ongoing. Traffic is still using the existing SR-56; however, motorists are
advised to use caution and watch for construction equipment adjacent to
roadway. Flaggers may be present to move equipment across roadway, unload
equipment, or complete utility work. The contractor will start grade work
inside Smithville City Limits between Dearman Street and East Bryant Street.
Traffic in this area will be shifted in the area to allow contractor to
complete work. A diversion remains in place for Williams Road to allow
contractor to construct new alignment. The speed limit has been reduced to 45
mph in the construction zone. Motorist should use caution in this area and
watch for flaggers and construction equipment.
[Jones
Bros. Contractors, LLC/Harris/CNT011]
FENTRESS
COUNTY SR-85 rock fall mitigation at LM 3.8: The
contractor will be on site continuing rock fall mitigation work at LM 3.8.
SR-85 in Fentress County will be closed from Sandy RD at LM 2.19 to East Obey
Lane at LM 5.67. This closure will remain until contract completion of
05/31/21. During this closure, a detour route will be in place to allow traffic
to navigate around the road closure.
[J and M
Grading Division, LLC/Moore/CNU276]
FENTRESS
AND OVERTON COUNTY SR-85 emergency slide repairs at various locations: The contractor continues work on
the Overton County side of SR-85 and the road remains closed from LM 17.5 to LM
22.2. This closure will remain in effect until approximately 05/28/21. The
contractor is currently working to stabilize the roadway and is completing
construction on the last scheduled roadway retaining wall. Motorists should
continue using the signed detour route until the roadway is opened back up.
[Wright
Brothers Construction Company, Inc./Moore/CNT154]
JACKSON
COUNTY SR-262 slope stabilization at LM 8.4: The contractor will be on site
continuing slope stabilization work at LM 8.4. TDOT has temporary traffic
signals in place on SR-262 reducing it to one lane from LM 8.1 to LM 8.6. The
eastbound lane will be closed for the duration of the project. Lane closures
will be in effect until the project completion which is anticipated on
02/05/21. Motorists are encouraged to use caution through the work zone and
obey posted speed limit.
[GeoStabilization
International, LLC /Maintenance/SWC191]
PUTNAM
COUNTY TDOT Maintenance on I-40 both directions from MM 267 to MM 304: From 02/02/21 through 02/04/21
TDOT Maintenance will be patching potholes on I-40 in Putnam Co. from MM 267 to
MM 304 in both directions. There will be intermittent lane closures using a
mobile operation from 8 AM to 4 PM.
PUTNAM
COUNTY Utility Work on SR-136 (S. JEFFERSON AVE.) both directions from LM 2.36
to LM 4.14: Shoulder
and single lane closure between Spring Street and I-40. Message and arrow
boards, signage, and cones will be present. Motorists should use caution through
the area and be aware of personnel and equipment between 9 AM and 3 PM
beginning 01/05/21 through 02/17/21.
PUTNAM
COUNTY Utility Work on SR-24 (MONTEREY HWY.) northbound from LM 33.53 to LM
36.37: Shoulder
and single lane closure between Bee Rock Road and West Bishop Avenue. Signage,
flaggers, and barrels will be present. Motorists should use caution through the
area and be aware of personnel and equipment between 8 AM and 4 PM beginning
11/30/20 through 02/12/21.
PUTNAM
COUNTY SR-135 (Burgess Falls Road) grading, drainage, signals and paving at the
intersection of West Cemetery Road (LM 6.6): Contractor
will be installing erosion control measures and beginning gas line relocation.
Motorists are advised to use caution while traveling through the work zone and
be alert of all signage, traffic control devices, personnel, and equipment.
[Rogers
Group, Inc./James/CNU270]
DISTRICT 28
CANNON COUNTY TDOT Bridge
Maintenance on SR-1 (JOHN BRAGG HWY.) westbound from LM 1.32 to LM 1.32: Bridge Maintenance will be performing regular
maintenance on the bridge located on SR-01 over Carson Fork Creek at LM 1.32,
west bound, on 01/28/21 from 8 AM until 3 PM. This project will require a
temporary closure of the Westbound lane and shoulder.
COFFEE COUNTY I-24 (MM 117)
improvement of ramps at Exit 117: I-24 WB between
MM 118 and MM 116, maintenance work will continue daily. There may be
alternating lane closures on WB between MM 116 to MM 118 to support
miscellaneous final work. Wattendorf Hwy. will have additional flagging
operations in place to support the construction of new turning lane. There will
be no impact to the entrance/exit ramp on I-24. Motorists are advised to use
caution while traveling through the work zone area and be alert to all traffic
signage, personnel, and equipment.
[Permitee/Hussein/PERMIT]
COFFEE COUNTY TDOT Bridge
Maintenance on SR-2 (HILLSBORO RD.) southbound from LM 16.78 to LM 16.78: Bridge Maintenance will be performing regular maintenance on the bridge
located on SR-02 over I-24 at LM 16.78, SB, on 02/02/21 from 8 AM until 3 PM.
This project will require a temporary closure of the Southbound lane and
shoulder.
COFFEE COUNTY Utility Work on SR-2
(US-41) both directions from LM 0 to LM 28.55: Mobile lane closure along SR-2 between Holly Court and Henley Lane.
Signage, flaggers, and cones will be present, motorists should be aware of
personnel and equipment between 9 AM and 2 PM between 11/30/20 through
04/02/21.
GRUNDY COUNTY Utility Work on SR-2
(US-41) both directions from LM 1.95 to LM 0: Mobile lane closure along SR-2 between Holly Court and Henley Lane.
Signage, flaggers, and cones will be present, motorists should be aware of
personnel and equipment between 9 AM and 2 PM between 11/30/20 through
04/02/21.
GRUNDY COUNTY Utility Work on SR-56
(--) both directions from LM 20.19 to LM 25.69: Mobile lane closures along SR-56 from the intersection of SR-56 and
SR-108 to the intersection of SR-56 and Store Door Road. Motorists should use
caution and be aware of personnel and equipment when traveling through the work
zones. Signage, cones, and flaggers will be present between 7 AM to 4 PM
starting 08/31/20 through 02/28/21.
GRUNDY COUNTY SR-56 slide repair
between LM 26.3 and LM 26.6: The road
will remain one lane controlled by a temporary traffic signal while contractor
completes slide repairs in the area. Motorists should use caution in the area
and watch for flaggers and equipment.
[Dement Construction Company, LLC/Harris/CNU355]
MARION COUNTY SR-156 resurfacing
from east of Orme Mountain Rd (LM 9.3) to near Elm Avenue (LM 14.5): Currently the contractor performing catch basin repair and replacing the
curb and gutters on SR-156. Occasionally, the road will be reduced to one lane
controlled by a flagger to accommodate the work being performed. Please use
caution when traveling through the area.
[Tinsley Asphalt, LLC /Voiles/CNU156]
MARION COUNTY SR-27 slope
stabilization at LM 27.9: local patching
will be done at this location 01/28/21, manual flagging will be used in
conjunction with the signal lights between 9:30 AM Eastern and 11 AM Eastern
[TDOT/Miner/MAINT]
MARION COUNTY Utility Work on SR-108
(STATE HWY. 108) both directions from LM 7.05 to LM 4.21: Mobile lane closures along SR-108 from the intersection of SR-108 and
Floyd Road to the intersection of SR-108 and Fish Branch Road. Motorists should
use caution and be aware of personnel and equipment when traveling through the
work zones. Signage, cones, and flaggers will be present between 8 AM to 4 PM
starting 01/18/21 through 3/26/21.
DISTRICT 29
BRADLEY COUNTY Utility Work on SR-2
(S. LEE HWY.) northbound from LM 8.21 to LM 8.44: Center lane closure between Victory Street SW and Golf Drive SW.
Signage, flaggers and cones will be present. Motorists should use caution
through the area and be aware of personnel and equipment between 8 PM and 6 AM
with an estimated completion 02/18/21.
BRADLEY COUNTY Utility Work on SR-74
(OCOEE ST. N.E.) both directions from LM 16.26 to LM 16.88: Shoulder and single lane closure between Westview Drive NW and Keith
Street NW. Signage and cones will be present. Motorists should use caution
through the area and be aware of personnel and equipment between 9 AM and 3 PM
with an estimated completion 02/28/21.
BRADLEY COUNTY SR-60 construction of
small drainage structures (LM 15.85 and LM 15.9): Work on this project is complete pending punchlist. The contractor may
have intermittent closures of the right northbound shoulder of SR-60 to work on
the punchlist. Motorists are advised to use caution entering the shopping
center at the intersection of 25th Street and Keith Street.
[Whaley Construction, LLC/Wagner/CNU227]
HAMILTON COUNTY SR-319 repair of the
bridge over the Tennessee River and Riverpark Drive (LM 2.2): The contractor will be performing repair operations to the bridge that
will require lane closures in both directions. Extra caution should be observed
of trucks entering and exiting the work-zone. During this report period the
contractor will have temporary lane closures in each direction. Additional
flaggers will be present as needed.
[Mid-State Construction Company,
Inc./Osbonlighter/CNU205]
HAMILTON COUNTY I-24 Replacement of
Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM
183: Lane shifts and single lane closures are in place
at North and South Terrace approaching the Belvoir Avenue Bridge. Single
alternating lane closures on I-24 EB and WB will be used on 01/28/21, and
01/31/21 through 02/03/21 from 9 PM and 6 AM. Additionally, there will be
single lane closures in the north and south directions of Germantown Road under
the I-24 Bridge and at the intersections of Germantown with North and South
Terrace. These closures will occur on 01/28/21 and 01/29/21, and between
01/01/21 and 02/03/21 from 9 AM to 6 AM the following morning. Motorists should
be aware of the Belvoir Avenue Bridge closure and detour that was put into place
on 04/20/20. There is a 45 MPH speed limit reduction throughout the project
corridor on I-24.
[Bell and Associates Construction,
LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24
Interchange Reconstruction: Phase 2 traffic
alignments have been implemented. Watch for trucks entering and exiting
project. Traffic should expect multiple lane shifts traveling through the
interchange. Lane closures will occur Sunday nights through Thursday nights
between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3
and I-24 EB MM 184.0 Traffic pacing may occur throughout interchange Sunday
nights through Thursday nights between 9 PM and 6 AM. Additionally, there may
intermittent shoulder closures at various locations for access to the median
and roadside areas. I-75 NB to I-24 WB split has been moved back 1500 feet from
its previous location. Welcome Center traffic intending to use I-24 WB now,
will have to detour on I-75 NB to Exit 3. Detailed detour information will be
available at the Welcome Center. The speed limit has been reduced to 45 MPH
throughout the interchange. ***TRAFFIC SHIFT on
02-01-2021, I-75 SB will be shifted after 9 PM near the interchange to
accommodate shoulder work.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY US-27 (I-124)
widening from I-24/US-27 interchange to north of the Olgiati Bridge over the
Tennessee River, including widening the Olgiati Bridge: Work on this project continues with activities occurring in the median and
shoulders of US-27. Motorists should be alert for construction vehicles
entering and exiting the activity area. Motorists should pay close attention to
the detour signage posted. The speed limit on US-27 in the construction zone
remains 45 MPH. Weather permitting, the contractor may implement temporary
lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At
least one lane will remain open in each direction on US-27. Note: Monday thru
Friday from 6 AM to 7 PM a minimum of two lanes will remain open both
northbound and southbound on US-27. Monday thru Friday from 7 PM to 6 AM and
Saturday and Sunday from 6 AM to 7 PM a minimum of one lane will remain open
both northbound and southbound on US-27. Thursday 01/28/21 thru Wednesday
02/03/21 from 7 AM to 6 PM and 7 PM to 6 AM, temporary lane closures will be in
place for southbound and northbound US-27 from the Olgiati Bridge to I-24 for
median work, striping, and painting operations. Saturday 01/30/21 and Sunday
01/31/21 from 8 AM to 8 PM, temporary double right lane closures will be in
place for southbound and northbound US-27 from the Olgiati Bridge to I-24 for
striping operations. Friday 01/29/21 thru Sunday 01/31/21 from 7 PM to 8 PM,
temporary lane closures will be utilized for west bound M.L. King Blvd.
traffic. Traffic will be shifted to one lane for west bound traffic for
crosswalk construction. State Trooper requested on Saturday 01/30/21 and Sunday
01/31/21for striping operations. RESTRICTIONS: I-124
(US-27) Northbound Exit 1C 4th Street Off Ramp No oversize/over dimensional
loads. I-124 (US-27) Southbound Exit 1A – 1B Martin Luther King Blvd Off Ramp
No oversize/over dimensional loads I-124 (US-27) Southbound on Ramps from
Martin Luther King Blvd No oversize/over dimensional loads.
[Dement Construction Company, LLC/Micka/CNP230]
HAMILTON COUNTY TDOT Maintenance on
I-24 both directions from MM 171 to MM 185: Litter pick up in median and on both sides of the interstate Monday
through Saturday.
HAMILTON COUNTY Utility Work on
SR-148 (LOOKOUT MTN. SCENIC HWY.) southbound at LM 0.10: Shoulder and single lane closure between Lula Lake Road and TN-GA State
Line. There will be temporary red lights to assist with the closure, as well as
signage and cones. Motorists should use caution through the area and be aware
of personnel and equipment between 9 AM and 3 PM from 12/15/20 through
02/28/21.
HAMILTON COUNTY Utility Work on
SR-153 (STATE HWY. 153) both directions from LM 0 to LM 4.0: Rolling roadblock between I-75 and SR-153 to SR-58 (Amnicola
Hwy). Traffic control trucks, message trucks, and signage will be present.
Motorists should use caution through the area and be aware of personnel and
equipment between 4 AM and 5 AM on 01/31/21.
HAMILTON COUNTY Utility Work on SR-2
(LEE HWY.) both directions from LM 17.12 to LM 17.12: Shoulder and single lane closure between Hwy 153 to Dupre Road. Signage
and cones will be present. Motorists should use caution through the area and be
aware of personnel and equipment between 9 AM and 2 PM starting 02/01/20
through 02/05/21.
HAMILTON COUNTY SR-29 (US-27) repair
of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge &
roadway repair on the SR-29 bridge over Big Soddy Creek. During this report
period the contractor will have traffic restricted with two lanes of SR-111
southbound closed. Also, during this report period, the contractor will have
two lanes of SR-29 north-bound closed. At least one lane of traffic in both
directions shall always remain open.
[Mid-State Construction Company,
Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-2 (US-64, US-11)
improvement of the intersection at Edgmon Road in Collegedale (LM 22.7),
including grading, drainage and paving: During
this report period, the contractor will be performing grading, drainage and
paving. Extra care should be taken while trucks and heavy equipment are
entering and exiting the roadway. The roadway may be temporarily restricted to
a one lane roadway by flagging operation.
[Talley Construction Company, Inc./Osbonlighter/CNU012]
HAMILTON COUNTY SR-317 (Apison Pike)
improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton
Lane: Lane closures and flagging operations will be
required on SR-317, Apison Pike, to install power poles and transfer lines. The
flagging operations will be performed on 01/28/21, 02/01/2021, 02/02/2021, and
02/03/2021 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours
per location. Eastview Terrace will also have short closures to connect
driveways to the new roadway. There will also be very short lane closures for
blasting that will last five minutes or less. The contractor will have
intermittent flagging operations during daytime non-peak hours for utility
work, delivery of materials and equipment.
[Wright Brothers Construction Company,
Inc./Osbonlighter/CNT336]
HAMILTON COUNTY The construction of
an S.I.A. to VW: The contractor will be grading, paving,
constructing retaining wall(s) and installing signals & lighting on S.I.A.
route connecting Ferdinand Piech Way & Volkswagen Dr. The roadway is not
open to traffic. The traveling public should be alert to the entrance and exit
of construction vehicles from the jobsite onto the connecting roadways.
Flaggers will be onsite directing traffic.
[Talley Construction Company,
Inc./Osbonlighter/CNU221]
POLK COUNTY Utility Work on SR-33
(HWY. 411) both directions from LM 9.9 to LM 14: Mobile lane closures SR-40 junction to Ocoee River Bridge as crews
transition work zone. Motorists should use caution and be aware of personnel
and equipment when traveling through the work zones. Signage, cones, and
flaggers will be present between 9 AM to 3 PM with an estimated completion of
03/31/21.
POLK COUNTY SR-40 (US-64) bridge
over the Ocoee River: During this reporting
period, the contractor will be working on foundations for the new bridge over
the Ocoee River. The right westbound shoulder of SR-40 (US-64) will be closed
for the duration of this work. Motorists are advised to reduce speed and to
watch for trucks entering/leaving the highway in the work zone.
[Charles Blalock and Sons, Inc./Wagner/DB1802]
POLK COUNTY SR-40 (US-64) emergency
slope stabilization near LM 20.5: During this
reporting period, the contractor will be hauling rock fill into the slide area.
The eastbound truck climbing lane on SR-40 (US-64) at LM 20.5 is closed and
will remain closed for the duration of construction. Motorists are advised to
reduce speed in the work zone and watch for trucks entering/leaving the
highway.
[Wright Brothers Construction Company,
Inc./Wagner/CNU909]
RHEA COUNTY The grading, drainage,
construction of bridges, paving and signals on a S.I.A. route serving Nokian
Tyres: Construction activity at the Nokian Tyres SIA
project continues just North of Dayton, TN. The travelling public should be
alert to construction vehicles entering and exiting the site. SR-29 traffic
will continue to experience slight lane shifts with no shoulders at the
entrance to the SIA roadway but there will be no lane closures on SR29.
[Dement Construction Company, LLC/Micka/CNU014]
REGION WIDE
REGION 2 The on-call concrete
pavement repair at various locations on various Interstate and State Routes: Vulcan Materials Company will be repairing concrete pavement in Hamilton
County on SR-2 near LM 7.72 and Washington St (E 20th & Washington near the
Mountain View Ford/Chevy dealerships) during the week. This work will shut down
various lanes as the work progresses leaving at least one lane open for each
direction of travel. Also, on Thursday 01/28/21 at 9:00 PM through Friday
01/29/21 at 6:00 AM the contractor will be saw cutting concrete pavement on
I-24 WB from mile marker 177 - mile marker 179 in lane #2 (the right lane). The
lane and ramp will be opened during the day on Friday. Then on Friday night 01/29/21
beginning at 8:00 PM through Monday 02/01/21 at 6:00 AM the contractor will be
pouring new concrete. Along with the lane closure, the Williams St. on-ramp to
I-24 WB will be completely closed. Please follow detour signs to get back to
I-24 WB. The I-24 WB lane #2 and the Williams St on-ramp will be closed while
work is performed on Thursday night from 9:00 PM - 6:00 AM, then closed again
from Friday night at 8:00 PM through Monday morning at 6:00 AM. Motorists are
advised to use caution while traveling through the work zone and be alert of
all traffic signage, personnel and equipment.
[Vulcan Construction Materials, LLC/Voiles/CNT380]
REGION 2 on-call guardrail repair
and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in
order to perform guardrail repair. These closures will take place on the
interstate nightly from 7 PM to 6 AM Sundays through Thursdays and daily on
state routes. At least one travel lane will always remain open to traffic on
the interstate, and flaggers will be present on state routes during any work
that is performed.
[Cumberland Guardrail, Inc./Harris/CNU107]
REGION 2 preventative and
unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation
System: The contractor may have short term shoulder and/or
lane closures in order to perform preventative or unscheduled maintenance to
the local SmartWay Intelligent Transportation System. At least one travel lane will
always remain open to traffic. Flaggers will assist with traffic control as
needed.
[NABCO Electric Company, Inc./Osbonlighter/CNT354]
REGION 2 sweeping and drain cleaning
on various interstate and state routes: There
will be an area wide sweeping operation on selected regional state routes and
interstates. This activity will be supported by a mobile lane closure. Hours of
activity are Sunday through Thursday night between 8 PM and 6 AM during this
reporting period
[Blevins Enterprises, Inc./Micka/CNT329]
REGION 2 TDOT Maintenance drainage
work: There will be possible short-term lane and shoulder
closures at various locations in Region 2 in order to clean rock and debris
from ditches on an as-needed basis. One lane will always be maintained.
[TDOT Operations/Maintenance/R2MAINT]
REGION 2 TDOT Maintenance pothole
repair and pavement patching: There will be
possible short-term emergency lane closures at various locations in Region 2 in
order to repair potholes and patch pavement on an as-needed basis. Depending on
location and severity these repairs may be done during the day or at night. In
addition to performing the work, regional Operations crews will also provide
traffic control.
[TDOT Operations/Maintenance/R2MAINT]
REGION 2 TDOT mowing operations: There will be possible short-term lane closures at
various locations on interstates and state routes in Region 2 in order to
perform mowing activities on an as-needed basis. In addition to performing the
work, regional Operations crews will also provide traffic control.
[TDOT/Maintenance/R2MAINT]
REGION 2 The random on-call cable
barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform
cable rail repair. Both travel lanes will always remain open to traffic on the
interstate during any work that is performed.
[LU, Inc./Harris/CNU303]
RESTRICTIONS
CLAY COUNTY - CNU198: Loads wider than 11' should seek alternate route.
HAMILTON COUNTY - CNP230: I-124 (US-27) Northbound Exit 1C 4th Street Off Ramp No oversize/over
dimensional loads. I-124 (US-27) Southbound Exit 1A – 1B Martin Luther King
Blvd Off Ramp No oversize/over dimensional loads I-124 (US-27) Southbound on
Ramps from Martin Luther King Blvd No oversize/over dimensional loads.
Motorists are encouraged to use
caution and obey reduced speed limits in all TDOT work zones, regardless of
lane closure activity.
Information in this report is
provided to the Department of Transportation by the contractors. Most work is
weather dependent and subject to change due to inclement weather. All times are
local.
From your desktop or mobile device,
get the latest construction activity and live streaming SmartWay traffic
cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular
phone for travel information, or follow us on Twitter at www.twitter.com/TN511
for statewide travel or Chattanooga area alerts @Chattanooga511
or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist
information tools wisely and Know Before You Go! by checking travel
conditions before leaving for your destination. Drivers should never tweet,
text, or talk on a cell phone while behind the wheel.
In 2016, the Tennessee Department of
Transportation lost three workers in the line of duty. All three were struck by
passing motorists. Those tragedies bring the total number of TDOT lives lost to
112. We don't want to lose another member of our TDOT family. We're asking you
to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.
###